20 persons completed 1/3rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
Work done = 1/3 Remaining work = 2/3 So for double work in same days we need double number of people i.e. 40. So, 20 men will be increased.