A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work for 10 days and B and C leave. How many days more will A take to finish the work?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
18
answered Sep 07, 2023 at 09:12

Your Answer