A and B complete a work in 6 days. If can A can complete the work in 14 days, in how many days B alone can do the same work.

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
1 days 5/7 hours