A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
5 days
answered Sep 07, 2023 at 09:12