A can do a piece of work in 3 days while B can do the same work in 4 days. If they work together for a total wages of ₹ 2800. how much does A get?
Asked Sep 07, 2023
Modified Sep 07, 2023
Viewed 0 times
▲
0
▼
Mathematics
Share
Share this question
Copy Link
Follow
asked Sep 07, 2023 at 09:12
A
Academy
0
comments
Sign in to add a comment
1 Answer
✓
▲
0
▼
As 1 days work = 1/3 Bs 1 days work = 1/4 As share : Bs share = (1/3) : (1/4) = (4/12) : (3/12) = 4 : 3 As share = (4/7) x 2800 = 4 x 400 = ₹ 1600