A can do a work in 12 days while B can do it in 15 days. They undertake to complete it together for Rs.450. what will be the share of A in this amount of money ?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
Rs.250
answered Sep 07, 2023 at 09:12

Your Answer