A complete 7/10 of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
40/3 days
answered Sep 07, 2023 at 09:12