A contractor undertook to do a work in 60 days. He employed 50 workers to carry out the job, but after 40 days he found that only half work had been done. Now, how many more worker should he employ to finish the work in time?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
50
answered Sep 07, 2023 at 09:12

Your Answer