A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
4 days
answered Sep 07, 2023 at 09:12