A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
30 days