Vandana can do a piece of work in 10 days. With the help of Ruchi, she can do the same work in 6 days. If they get ₹ 200 for that work, then what will be the share of Ruchi in the received remuneration?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
Vandanas 1 days work = 1/10 (vandana + Ruchi)s 1 day work =1/6 ∴ Ruchis 1 days work = 1/6 - 1/10 = (10 - 6)/ (6 x 10) = 4 / 60 = 1/15 ∴ Vandanas share : Ruchis share = 1/10 : 1/15 = 3/30 : 2/30 = 3 : 2 Ruchis share = 2/5 x 200 = ₹ 80