x does 1/4 of a job in 6 days. y completes rest of the job in 12 days. Then x and y could complete the job together in = ?

Asked Sep 07, 2023 Modified Sep 07, 2023 Viewed 0 times
0
asked Sep 07, 2023 at 09:12
1 Answer
0
9 3/5 days