Given that
(10M + 15W) x 6 days = 1M x 100 days
=> 60M + 90W = 100M
=> 40M = 90W
=> 4M = 9W.
From the given data,
1M can do the work in 100 days
=> 4M can do the same work in 100/4= 25 days.
=> 9W can do the same work in 25 days.
=> 1W can do the same work in 25 x 9 = 225 days.
Hence, 1 woman can do the same work in 225 days.