A calculator is bought for тВ╣ 350 and sold at a gain of 15%. What will be the selling price of calculator (in тВ╣) ?

A can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work ?

A can complete a certain work in 4 minutes, B in 5 minutes, C in 6 minutes, D in 10 minutes and E in 12 minutes. The average number of units of work completed by them per minute will be = ?

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?

A can complete a piece of work in 10 days, while B alone can complete it in 15 days. They work together for 5 days and rest of the work is done by C in 2 days. If they receive $ 450 for the whole work, how should they divide the money?

A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

A can complete a work in 15 days and B can complete the work in 20 days. If B works for 8 days and left the job, then in how many days the A can complete the remaining job ?

A can complete a work in 2 days and B can complete the work in 3 days. With the help of C they together completed in 1 day. C alone can complete the work in ?